New Headworks Facility

Overview

Built in 1952, the Southeast Treatment Plant is the City's largest wastewater treatment facility handling nearly 80% of San Francisco's combined storm and wastewater every year, however, many of its facilities are past their useful life and generate odors that impact the neighborhood.

The SFPUC is investing over $3 billion in critical upgrades transform this facility in the Bayview into a modern resource recovery center, including construction of the New Headworks Project. By doing so, we will continue to protect our communities and the environment while creating an attractive workplace and neighborhood asset that serves the entire City for decades to come.

When complete, the plant will work better, look better, and smell better for the neighborhood, our staff, and the entire City!

CONSTRUCTION UPDATES (Winter 2024-2025)

Evans Avenue Restoration

Unforeseen site conditions have delayed the restoration work taking place on Evans Avenue, which includes sidewalk and curb work, as well as installation of new lighting and additional tree planting. The work began in November 2024 and was expected to be completed by late January 2025.

Updated Duration: Work began in late November 2024 and is now expected to be complete mid-March 2025. Expected upcoming work includes:

  • Grading and pouring the sidewalk on south Evans Avenue between February 3 - February 12, 2025
  • Paving Evans Avenue between February 20 - February 21, 2025
  • Installing trees and landscaping between February 20 - March 3, 2025
  • Construction Start: Spring 2018
  • Construction End: 2025
  • Project Phase: Construction