Water Main Installation Process
The San Francisco Public Utilities Commission owns and operates more than 1,200 miles of water pipelines in San Francisco. Those pipes, also called water mains, deliver high quality drinking water to your tap. Many of those water mains are aging and need to be replaced. Some are almost 100 years old.
The process of replacing those water mains involves multiple steps, so construction will not occur continuously. Crews will need to return to the same block several times to work, often with months between visits.
If we are doing water main replacement work in your area, it will ensure that your drinking water supply remains safe and reliable.
-
Locate Underground Utilities (called Potholing)
Crews dig small holes in the street along the pipeline alignment to confirm the location of the underground utilities, such as cable, gas, fiber, and wastewater lines. -
Mobilization
Crews bring equipment and supplies and store them on the street or another nearby location where they will be needed. -
Water Main Installation
Crews sawcut and remove the asphalt and concrete from the area where the new water main will be placed. They dig a trench down to the depth of the new water main. The new water pipe is lowered into the ground, one pipe section at a time. These pipeline sections are connected together in the trench and this process continues until they reach a point where they can be connected to the existing water main network. -
Backfill Trench and Temporary Street Restoration
Crews will carefully place sand and dirt – called backfill material – into the trench. Temporary asphalt will be placed on top of the trench so people can drive over it.
Final restoration of the asphalt in the street will happen later in the project. -
Testing the New Water Main
Once the new water main segment has been put into the trench, crews will test the line to ensure there are no leaks. They do this by putting water at higher pressures in the new pipeline segment for a period of time. If no leaks appear, the pipe passes. -
Connection to Existing Water Main
Once a new pipeline passes the leak test, crews will complete a connection to the network between the newly installed water main and the existing water main on the street that delivers water to the area.
Water service to a property would be temporarily impacted during this time. -
Disinfection
At this stage, the team flushes the water main and injects chlorine inside the pipe to ensure thorough disinfection of the pipe interior. Crews then flush the main again and test the water quality in the mains. Once water quality passes, the main is ready to serve customers. -
Connection to Customers
San Francisco Water Division crews construct new service lines from the new water main to customer’s properties. This enables customers to receive water from the new water main.
Water service to a property would be temporarily impacted during this time. -
Remaining Connections to New or Existing Water Main
Crews continue to dig and construct new connections between the new water main and the existing water main delivering water to the area.
Water service to a property would be temporarily impacted during this time. -
Backfill Trench and Temporary Street Restoration as Connections are Finished and Tested
Crews will carefully place sand and dirt – called backfill material – into the trenched areas where the new pipeline connections have been made. Temporary asphalt is placed on top of the trench so people can drive over it.
Final restoration of the asphalt in the street will happen later in the project. -
Repeat in different segments all along the project area
-
Final Paving Restoration
When the entire project is complete, oftentimes months after the work on any particular block is completed, crews will perform final pavement restoration in the project area.