Hampshire and York Streets Utility Upgrade Project
Overview
Critical upgrades to our aging water and sewer infrastructure are planned for:
- Hampshire and York streets between Mariposa and Cesar Chavez streets
- Bryant Street between Precita Avenue and 26th Street
- 23rd and 25th streets between Hampshire Street and Potrero Avenue
- 26th Street between Bryant and Hampshire streets
- Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp
This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration.
Construction Look Ahead
Week of December 9th
- Excavate connection pits and service changeovers - 25th Street between Hampshire Street and Potrero Avenue
- Curb ramp installation - 18th and York streets
Week of December 16th
- Excavate connection pits and service changeovers - 25th Street between Hampshire Street and Potrero Avenue
- Street base concrete restoration - Hampshire Street between 24th and Mariposa streets
- Curb ramp installation - 18th and York streets
Week of December 23rd
- No work scheduled