Hampshire and York Streets Utility Upgrade Project
Overview
Critical upgrades to our aging water and sewer infrastructure are planned for:
- Hampshire and York streets between Mariposa and Cesar Chavez streets
- Bryant Street between Precita Avenue and 26th Street
- 23rd and 25th streets between Hampshire Street and Potrero Avenue
- 26th Street between Bryant and Hampshire streets
- Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp
This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration.
Construction Look Ahead
Week of November 18th
- Excavate service transfer pits - 25th Street between Hampshire Street and Potrero Avenue
- Street base concrete restoration - York Street between 23rd and 24th streets
Week of November 25th
- Excavate and water pipeline installation - 18th Street between Hampshire Street and Potrero Avenue
- Excavate service transfer pits and perform service changeovers - 25th Street between Hampshire Street and Potrero Avenue
- Street base concrete restoration - York Street between 22nd and 24th streets
Week of December 2nd
- Service changeovers - 25th Street between Hampshire Street and Potrero Avenue
- Street base concrete restoration - York Street between 20th and 21st streets; Hampshire Street between Cesar Chavez and 25th streets