Hampshire and York Streets Utility Upgrade Project

Overview

Critical upgrades to our aging water and sewer infrastructure are planned for:

  • Hampshire and York streets between Mariposa and Cesar Chavez streets
  • Bryant Street between Precita Avenue and 26th Street
  • 23rd and 25th streets between Hampshire Street and Potrero Avenue
  • 26th Street between Bryant and Hampshire streets
  • Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp 

This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration. 

Construction Look Ahead

Week of November 18th

  • Excavate service transfer pits - 25th Street between Hampshire Street and Potrero Avenue
  • Street base concrete restoration - York Street between 23rd and 24th streets

Week of November 25th

  • Excavate and water pipeline installation - 18th Street between Hampshire Street and Potrero Avenue
  • Excavate service transfer pits and perform service changeovers - 25th Street between Hampshire Street and Potrero Avenue
  • Street base concrete restoration - York Street between 22nd and 24th streets

Week of December 2nd

  • Service changeovers - 25th Street between Hampshire Street and Potrero Avenue
  • Street base concrete restoration - York Street between 20th and 21st streets; Hampshire Street between Cesar Chavez and 25th streets

 

Map showing where construction will take place for the Hampshire and York streets project

  • Construction Start: July 2023
  • Construction End: December 2025
  • Project Phase: Construction