Hampshire and York Streets Utility Upgrade Project

Overview

Critical upgrades to our aging water and sewer infrastructure are planned for:

  • Hampshire and York streets between Mariposa and Cesar Chavez streets
  • Bryant Street between Precita Avenue and 26th Street
  • 23rd and 25th streets between Hampshire Street and Potrero Avenue
  • 26th Street between Bryant and Hampshire streets
  • Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp 

This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration. 


Construction Look Ahead

Week of March 17

  • Pipeline connections (to be performed at night) - Intersection of Hampshire and Mariposa streets (3/18 from 7-11pm); Intersection of Hampshire and Cesar Chavez streets (3/19 from 10pm - 2am)
  • T-trench and street base concrete restoration - Bryant Street between Precita and 26th streets
  • Connection pit restoration - Intersection of Hampshire and Mariposa streets; Intersection of Hampshire and Cesar Chavez streets 

Week of March 24

  • Excavate service transfer pits and service changeovers - Hampshire Street between 18th and Mariposa streets
  • T-trench and street base concrete restoration - Cesar Chavez on-ramp
  • Final street paving - Cesar Chavez on-ramp

 

Map showing where construction will take place for the Hampshire and York streets project

  • Construction Start: July 2023
  • Construction End: December 2025
  • Project Phase: Construction