Hampshire and York Streets Utility Upgrade Project
Overview
Critical upgrades to our aging water and sewer infrastructure are planned for:
- Hampshire and York streets between Mariposa and Cesar Chavez streets
- Bryant Street between Precita Avenue and 26th Street
- 23rd and 25th streets between Hampshire Street and Potrero Avenue
- 26th Street between Bryant and Hampshire streets
- Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp
This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration.
Construction Look Ahead
Week of January 6th
- Pipeline connections - Intersection of 25th and Hampshire streets; Hampshire Street between 24t and 25th streets
- Street base concrete restoration - Hampshire Street between Cesar Chavez and 25th streets
- Curb ramp installation - 18th and York streets
Week of January 13th
- Pipeline connections - Intersection of 25th and Hampshire streets; Hampshire Street between 24t and 25th streets
- Curb ramp installation - Intersection of 18th and York streets; Intersection of 18th and Hampshire streets
- Pavement restoration - Hampshire Street between 24th and 25th streets
Week of January 20th
- Pipeline connections - Intersection of 25th and Hampshire streets
- Curb ramp installation - Intersection of 18th and Hampshire streets
- Pavement restoration - Hampshire Street between 24th and 25th streets