Hampshire and York Streets Utility Upgrade Project

Overview

Critical upgrades to our aging water and sewer infrastructure are planned for:

  • Hampshire and York streets between Mariposa and Cesar Chavez streets
  • Bryant Street between Precita Avenue and 26th Street
  • 23rd and 25th streets between Hampshire Street and Potrero Avenue
  • 26th Street between Bryant and Hampshire streets
  • Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp 

This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration. 


Construction Look Ahead

Week of February 24th

  • T-trench and street base concrete restoration - Hampshire Street between 21st and 24th streets
  • Catch basin installation - Intersection of 26th and York streets
  • Curb ramp installation - Intersection of 26th and Hampshire streets
     
  • Final street paving - York Street between Mariposa and 21st Street
    • Streets will be closed to traffic with no street parking or driveway access during working hours of 7am to 5pm. Parking and driveway access allowed from 5:15pm to 6:45am. 
      • Wednesday, February 26: Street grinding between Mariposa and 21st Street; Minimal impacts to driveway access. 
      • Thursday, February 27: Asphalt repaving between Mariposa and 19th Street; Streets closed 7am - 5pm
      • Friday, February 28: Asphalt repaving between 19th and 21st Street; Streets closed 7am - 5pm


Week of March 3rd

  • Curb ramp installation - Intersection of 26th and Hampshire streets
  • Excavate service transfer pits and service changeovers - Hampshire Street between 18th and Mariposa streets
  • Excavate connection pits - Hampshire Street at Cesar Chavez Street
  • T-trench and street base concrete restoration - Hampshire Street between 21st and 24th streets; Cesar Chavez on-ramp
  • Concrete bus pad restoration - Hampshire Street between 24th and 25th streets
     
  • Final street paving - York Street between 21st and 24th streets and 25th to 26th streets; Hampshire Street between Cesar Chavez and 24th Street; 25th Street between Potrero and Hampshire Street
    • ​​​​​​​Streets will be closed to traffic with no street parking or driveway access during working hours of 7am to 5pm. Parking and driveway access allowed from 5:15pm to 6:45am. 
      • Monday, March 3: Street grinding on York St between 21st and 24th Street, and 25th to 26th Street; Minimal impacts to driveway access. 
      • Tuesday, March 4: Asphalt repaving on York Street between 21st and 24th Street; Streets closed 7am - 5pm
      • Wednesday, March 5: Street grinding on Hampshire St between Cesar Chavez and 24th Street; and 25th Street between Potrero and Hampshire St; Minimal impacts to driveway access.
      • Thursday, March 6: Asphalt repaving on York St between 25th and 26th St, and Hampshire between 24th and 25th St; Streets closed 7am - 5pm
      • Friday, March 7: Asphalt repaving on Hampshire St between Cesar Chavez and 25th Street; and 25th Street between Potrero and Hampshire St; Streets closed 7am - 5pm

 

 

Map showing where construction will take place for the Hampshire and York streets project

  • Construction Start: July 2023
  • Construction End: December 2025
  • Project Phase: Construction