Diamond Heights Water Main Replacement

Overview

As of June 7, 2024, all work on this project has been completed. The project included the installation of 16-, 12-, and 8-Inch ductile iron water mains, built curb ramps to facilitate the accessibility in accordance with the Americans with Disabilities Act, and restored asphalt and concrete street surfaces within the project area. Project area included:

  1. In the west at Portola Drive from 200 feet west of Clipper Street to 200 feet east of Clipper Street, Clipper Street from Portola Drive to Diamond Heights Boulevard, Diamond Heights Boulevard from Clipper Street to Duncan Street and
  2. In the east on Diamond Street from 27th Street to Diamond Heights Boulevard, 28th and Duncan streets from Douglass to Noe streets, Valley Street from Diamond to Noe streets, and Noe Street from Duncan to Valley streets.
  • Construction Start: June 2022
  • Construction End: June 2024
  • Project Phase: Construction