Hampshire and York Streets Utility Upgrade Project
Overview
Critical upgrades to our aging water and sewer infrastructure are planned for:
- Hampshire and York streets between Mariposa and Cesar Chavez streets
- Bryant Street between Precita Avenue and 26th Street
- 23rd and 25th streets between Hampshire Street and Potrero Avenue
- 26th Street between Bryant and Hampshire streets
- Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp
This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration.
Construction Look Ahead
Week of March 17
- Pipeline connections (to be performed at night) - Intersection of Hampshire and Mariposa streets (3/18 from 7-11pm); Intersection of Hampshire and Cesar Chavez streets (3/19 from 10pm - 2am)
- T-trench and street base concrete restoration - Bryant Street between Precita and 26th streets
- Connection pit restoration - Intersection of Hampshire and Mariposa streets; Intersection of Hampshire and Cesar Chavez streets
Week of March 24
- Excavate service transfer pits and service changeovers - Hampshire Street between 18th and Mariposa streets
- T-trench and street base concrete restoration - Cesar Chavez on-ramp
- Final street paving - Cesar Chavez on-ramp