Hayes Valley Sewer Improvements Project
Overview
As part of the SFPUC's wastewater capital investments, the Hayes Valley Sewer Improvements Project will rehabilitate the existing 100+ year old sewer mains located under several streets located in Hayes Valley.
Please check this project page for timely updates about the construction schedule and upcoming locations. To receive these updates via email, please complete the form on the right hand side of this page.
Construction Update February 2025
We are ramping up our sewer main and lateral lining sequences, which means that our crews will be implementing the Cured-In-Place-Lining method throughout various project locations in the coming months.
Schedule is subject to change, work hours for night work will begin Fridays at 7PM and crews will wrap on Sundays at 11PM. Normal work hours are 7AM to 4PM (M-F).
Oak Street (Laguna to Octavia)
- None scheduled.
Oak Street (Octavia to Gough)
- Expect continuous work from February 21 to February 25.
Oak Street (Gough to Franklin)
- Expect continuous work from February 21 to February 23.
- Expect continuous work from February 28 to March 2.
Oak Street (Franklin to Van Ness)
- Expect continuous work from February 28 to March 2.
Page Street (Octavia to Franklin)
- Expect continuous work from February 18 to February 20.
Franklin Street (Golden Gate to Fulton)
- None scheduled.
Sutter Street (Scott to Pierce)
- Expect continuous work from February 25 to February 26.