Various Locations Brick Sewer Improvements Project
- phone(415) 554-3289
- mail_outline ssip@sfwater.org
Overview
As part of the SSIP investments, the Various Locations Brick Sewer Improvements Project will rehabilitate the existing 100-year-old sewer mains located under several streets.
- Construction Start: Early 2023
- Construction End: Winter 2023
- Project Phase: Construction
-
Project Background
To minimize impacts to the roadway and adjacent residences and businesses, most of the sewer rehabilitation work will be performed using a trenchless method called Cured-In-Place-Pipe (CIPP). Construction will include improvements to sewer lower laterals within the project area. In some locations, street excavation may be required, and advance notice will be provided.
Project Benefits:
- Address aging sewer system infrastructure
- Increase reliability of our City’s critical sewer system infrastructure
About the SSIP
The San Francisco Public Utilities Commission (SFPUC) recently launched the Sewer System Improvement Program (SSIP), a citywide investment to upgrade our aging sewer system and provide a more reliable, sustainable, and seismically safe system now and for future generations. The SSIP includes a series of facility upgrades at the Southeast Treatment Plant (SEP) located in the Bayview neighborhood of San Francisco.
-
What to Expect During Construction
2 Week Look-Ahead Schedule (subject to change)
Currently Active
- Leavenworth Street, between California and Bush Streets
- Work Hours: Monday-Friday at 9:00am-3:00pm
- Schedule
- Ongoing work until the week of March 13: Manhole construction
- March 9: Sewer cleaning and inspection
Construction Coming Soon
- Columbus Avenue, between Greenwich and Powell Streets
- Work Hours: Monday-Friday at 7:00am-5:00pm
- Schedule
- March 1: Sewer cleaning and inspection
- *Commercial Street, between Grant Avenue and Montgomery Streets
- Work Hours: Monday-Friday at 8:00am-5:00pm
- Schedule
- Week of March 13: Sewer cleaning and inspection
- *Access: This street will be closed to both pedestrians and vehicles during working hours. If necessary, access may granted upon request- please reach out if you have any questions or concerns.
- Eddy Street, between Mason and Cyril Magnin Streets
- Work Hours: Monday-Friday at 9:00am-3:00pm
- Schedule
- Week of March 13: Sewer cleaning and inspection
- Franklin Street, between Union and Green Streets
- Work Hours: Monday-Friday at 9:00am-3:00pm
- Schedule
- March 8: Sewer cleaning and inspection
- March 9-13: Replace manholes
- Geary Boulevard, between Van Ness Avenue and Polk Street
- Work Hours: Monday-Friday at 9:00am-3:00pm
- Schedule
- Week of March 13: Sewer cleaning and inspection, manhole excavation and replacement
- Hyde Street, between California and Pine Streets
- Work Hours: Monday-Friday at 9:00am-3:00pm
- Schedule
- Week of February 27: Sliplining work
- Weeks of March 6 and 13: Sewer construction and manhole excavation continues
- Montgomery Street, between Broadway and Pacific Avenues & Montgomery/Vallejo Street intersection
- Work Hours: Monday-Friday at 8:00am-5:00pm
- Schedule
- Week of March 13: Sewer cleaning and inspection
- Powell Street, between Greenwich and Filbert Streets
- Work Hours: Monday-Friday at 8:00am-5:00pm
- Schedule
- February 27-28: Sewer cleaning and inspection
- Powell Street, between Union and Green Streets
- Work Hours: Monday-Friday at 8:00am-5:00pm
- Schedule
- Week of March 6: Sewer cleaning and inspection
- Powell Street, between Pacific Avenue and Jackson Street
- Work Hours: Monday-Friday at 8:00am-5:00pm
- Schedule
- March 10 and 13: Sewer cleaning and inspection
- Union Street, between Powell and Stockton Streets
- Work Hours: Monday-Friday at 9:00am-3:00pm
- Schedule
- Week of March 6: Sewer cleaning and inspection
Schedule Pending
- Golden Gate Avenue and Hyde Street intersection
- Anticipated Work Hours: Monday-Friday at 10:00pm-6:00am
- Schedule
- No work anticipated to occur in the next 2 weeks
- Kearny Street, between Clay and Sacramento Streets
- Anticipated Work Hours: Monday-Friday at 9:00am-3:00pm
- Schedule
- No work is anticipated to occur in the next 2 weeks
Crews will be conducting sewer work at the locations listed below. “No parking” signs will be posted in advance. *Locations with through access will continue to be available, flaggers will be on-site as needed, and detour signage will be posted. There will be necessary traffic control for public and worker safety. Sewer services will not be interrupted during construction.
SEWER SERVICE: These services will NOT be interrupted during construction.
PARKING: Street parking will be impacted near construction zones. “No-parking” signs will be posted 72 hours in advance.
TRAFFIC: Partial and/or full lane closures may be necessary to ensure safety of workers and the public. Advance notice and detour signage will be provided, as needed.
MUNI: Bus stops may be impacted during SFMTA’s transit work. For transit and bus stop work, please call (415) 701-2311 for temporary bus stops information.
ACCESS: Follow posted signage on site. Businesses and residents in the work zone will maintain access to their driveways and entrances during construction.
NOISE: Neighbors may hear construction noise periodically. Noisy work will be conducted in compliance with the San Francisco Noise Ordinance.
ODORS: If necessary, odor control measures will be in place during construction. Please see CIPP page for more information sfwater.org/cipp.
NOTICE: Residents and businesses within the project area will be notified before construction begins.
- Leavenworth Street, between California and Bush Streets
-
Project Materials