East SOMA Sewer Improvements Project
Overview
The East SOMA Sewer Improvements Project will rehabilitate the existing 100-year-old sewer mains and sewer lower laterals located under several streets highlighted on the Project Maps.
Please check this project page for timely updates about the construction schedule and upcoming locations. To receive these updates via email, please complete the form on the right-hand side of this page.
Week of March 3:
3rd Street (King and Berry):
- Crews will be paving the areas around newly installed manhole on March 6th.
Howard Street (2nd and 1st):
- Culvert lining will occur on March 6th.
- Excavation and replacement of laterals will occur from March 3rd to March 7th.
Bryant Street (3rd and 2nd):
- Cleaning and inspection of sewer main will occur March 7th.
- Weekend work beginning March 7th is pending.
Mission Street (7th and 6th):
- Excavation of manhole will occur on March 3rd to March 5th.
- Construction on sewer manhole will occur March 6th to March 7th.
- Excavation of large manhole will occur on March 7th.
- Sewer main lining anticipated to begin Late April 2025, with inspection and cleaning anticipated to begin Late March.
Mission Street (6th and 5th):
- Construction of sewer manhole to occur March 3rd to March 5th.
7th Street (Mission and Market):
- No work scheduled for week of March 3rd.
- Sewer main lining anticipated to begin Late April 2025, with inspection and cleaning anticipated to begin Late March.
3rd Street (Folsom and Harrison):
- Crews will be in the area lining one culvert on March 7th.
- Sewer main inspections anticipated to occur Early April, schedule for lining of the sewer main is pending.
Howard Street (Fremont and Main):
- Work planned for this area anticipated to begin in Late April 2025.