Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of April 21
- Excavate and perform service changeovers: Jersey Street between Douglass and Castro streets; Elizabeth Street between Castro and Hoffman streets
Week of April 28
- Excavate and perform service changeovers: Elizabeth Street between Castro and Hoffman streets
- Excavate and 8" water pipeline installation: Diamond Street between 23rd and 25th streets
- Water pipeline connections (Night work; will involve a temporary interruption of water service; impacted addresses will receive advance notification):
- Intersection of Jersey and Vicksburg streets - Monday, April 28 (10pm - 2am)
- Intersection of Jersey and Church streets - Monday, April 28 (10pm - 2am)
Week of May 5
- Excavate and perform service changeovers: Elizabeth Street between Castro and Hoffman streets; Jersey Street between Noe and Castro streets
- Excavate and 8" water pipeline installation: Diamond Street between 23rd and 25th streets
*Schedule subject to change