Active Alerts

If you are experiencing a water, power, or sewer emergency or service problem call our 24-hour hotline at 3-1-1 or (415) 701-2311 from outside SF or log on at sf311.org. Learn more or review active service alerts.

Noe Valley Water Main Replacement Project

Overview

Critical upgrades to our aging water infrastructure are planned for:

  • Jersey Street between Douglass and Church streets
  • Elizabeth Street between Hoffman and Castro streets
  • Diamond Street between 23rd and 26th streets
  • Douglass Street between 23rd and 25th streets

This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.

 

  • Construction Start: October 2024
  • Construction End: November 2026
  • Project Phase: Construction