Sewer Construction Look Ahead:
Week of December 16 -- Excavate and install new sewer main along Precita Avenue, starting at Harrison Street and continuing to Folsom Street. This will involve traffic detours and closure of Precita Avenue to westbound traffic starting at Harrison Street. Parents dropping off or picking up students at Leonard Flynn Elementary School should follow the coned path on Harrison Street. Flaggers will be present to help facilitate traffic flow.
Week of December 23 -- Contractor will not be working Dec. 23-27.
Week of December 30 -- Contractor to resume sewer installation work on Precita from Harrison to Folsom. Contractor will not be working Jan. 1.
Week of January 6 -- Contractor will continue installing sewer on Precita from Harrison to Folsom.
Week of January 13 -- Contractor will begin sewer lateral replacement on Precita from Folsom to Alabama.
Water Construction Look Ahead:
Start of Water Pipeline Construction is delayed until late March or early April 2025.