East SOMA Sewer Improvements Project

Overview

The East SOMA Sewer Improvements Project will rehabilitate the existing 100-year-old sewer mains and sewer lower laterals located under several streets highlighted on the Project Maps.

Please check this project page for timely updates about the construction schedule and upcoming locations. To receive these updates via email, please complete the form on the right-hand side of this page.

Week of April 14:

3rd Street (King and Berry):

  • No construction scheduled for week.

Howard Street (2nd and 1st):

  • No construction scheduled for week.

Bryant Street (3rd and 2nd):

  • No construction scheduled for week.

Mission Street (7th and 6th):

  • Backfilling and shoring of large manhole will occur April 18.
  • Excavation and replacement of sewer laterals will occur April 14 to April 18 and continue into the next week.

Mission Street (6th and 5th):

  • No construction scheduled for the week.
  • Sewer lining anticipated to begin week of May 12, prior noticing will be provided. 

7th Street (Mission and Market):

  • No construction scheduled for the week.

3rd Street (Folsom and Harrison):

  • Construction of sewer manhole will conclude on April 14 (West of Harrison).
  • Construction of sewer manhole will conclude on April 17 (East of Folsom).
  • Crews will be performing lining for 1 culvert on April 18.

Howard Street (Fremont and Main):

  • No work schedule for the week.

Schedule Subject to Change, last updated on 04/14/2025. Have questions? Please reach out to us by email at ssip@sfwater.org with 'East SOMA' in the subject line.

  • Construction Start: Late 2024
  • Construction End: Late 2025
  • Project Phase: Construction