Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of October 27
- Curb ramp installation: Intersection of Diamond Street and Elizabeth Street
Week of November 3
- Curb ramp installation: Intersections of Diamond and Elizabeth streets and Douglass and Elizabeth streets
- Service changeovers: Douglass Street between 23rd and 25th streets
Week of November 10
- Curb ramp installation: Intersection of Douglass and Elizabeth streets
- Service changeovers: Elizabeth Street between Douglass and Hoffman streets
*Schedule subject to change