Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
- 25th Street between Douglass and Diamond Streets - ADDED TO THE PROJECT NOVEMBER 2025
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of April 6
- Excavate and install 16-inch water main: Douglass Street between 24th and 25th streets
- Water main connections: Jersey Street between Diamond and Douglass streets; and Douglass Street between 24th and Jersey streets
Week of April 13
- Excavate and install 8-inch and 16-inch water main: Douglass Street between 24th and 25th streets
- Water main connections: Jersey Street between Diamond and Douglass streets; and Douglass Street between 24th and Jersey streets
Week of April 20
- Excavate and install 8-inch water main: Douglass Street between 24th and 25th streets
- Final street paving: Jersey Street between Castro and Diamond streets; Elizabeth Street between Diamond and Hoffman streets
*Schedule subject to change