Noe Valley Water Main Replacement Project

Overview

Critical upgrades to our aging water infrastructure are planned for:

  • Jersey Street between Douglass and Church streets
  • Elizabeth Street between Hoffman and Castro streets
  • Diamond Street between 23rd and 26th streets
  • Douglass Street between 23rd and 25th streets

This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.


Construction Look Ahead*

Week of March 10

  • Excavation and installation of 8" water pipeline: Jersey Street between Noe and Castro streets
  • Sawcutting trench for pipeline installation: Jersey Street between Castro and Douglass streets
  • Excavate connection pits: Jersey Street between Church and Noe streets


Week of March 17

  • Excavation and installation of 8" water pipeline: Jersey Street between Castro and Douglass streets
  • Excavate connection pits: Jersey Street between Noe and Castro streets


Week of March 24

  • Excavation and installation of 8" water pipeline: Jersey Street between Castro and Douglass


*Schedule subject to change

**Please note that work on Elizabeth Street has been postponed until late March.

  • Construction Start: October 2024
  • Construction End: November 2026
  • Project Phase: Construction