Noe Valley Water Main Replacement Project
Overview
Critical upgrades to our aging water infrastructure are planned for:
- Jersey Street between Douglass and Church streets
- Elizabeth Street between Hoffman and Castro streets
- Diamond Street between 23rd and 26th streets
- Douglass Street between 23rd and 25th streets
This project will include the installation of 8" and 16" ductile iron water mains and pavement restoration.
Construction Look Ahead*
Week of March 24
- Excavation and installation of 8" water pipeline: Elizabeth Street between Castro and Douglass streets
- Excavate connection pits: Jersey Street between Douglass and Castro streets
- Sawcutting trench for pipeline installation: Elizabeth Street between Castro and Hoffman streets
- Potholing (locating underground utilities): Diamond Street between 23rd and 26th streets
Week of March 31
- Excavation and installation of 8" water pipeline: Elizabeth Street between Castro and Douglass streets
- Excavate and perform service changeovers: Jersey Street between Church and Noe streets
Week of April 7
- Excavate and perform service changeovers: Jersey Street between Church and Noe streets; Jersey Street between Douglass and Castro streets
*Schedule subject to change