Hayes Valley Sewer Improvements Project
Overview
As part of the SFPUC's wastewater capital investments, the Hayes Valley Sewer Improvements Project will rehabilitate the existing 100+ year old sewer mains located under several streets located in Hayes Valley.
December 2024 Construction Update
- Starting the week of December 2, crews will mobilize for manhole and sewer lateral upgrades along Franklin Street between Oak Street and Page Street.
- Starting mid December, crews will mobilize for manhole and sewer lateral upgrades along Franklin Street between Golden Gate Avenue and McAllister Street.
- For both locations:
- Work sites will be located within the center lane of traffic and intersection. Through traffic will be maintained on all impacted roads with traffic control measures in place.
- Expect some impacts to street parking, see posted signs.
- These activities will have an estimated duration of 5 weeks.
Access to properties will be maintained. Expect noise, vibration, and odor impacts while this work is being completed.
Please check this project page for timely updates about the construction schedule and upcoming locations. To receive these updates via email, please complete the form on the right hand side of this page.