Hayes Valley Sewer Improvements Project
Overview
As part of the SFPUC's wastewater capital investments, the Hayes Valley Sewer Improvements Project will rehabilitate the existing 100+ year old sewer mains located under several streets located in Hayes Valley.
Construction Update: January 2025
We are ramping up our sewer main and lateral lining sequences, which means that our crews will be implementing the Cured-In-Place-Lining method throughout various project locations in the coming months.
Scott Street
- Expect continuous work from Tuesday, January 14 to Friday, January 17
- Lining hours: 7AM to 4PM
Sutter Street
- Expect continuous work from Monday, January 20 to Thursday, January 23
- Work hours: 8AM to 11PM
- Lining hours: 7AM to 4PM
Oak Street (Laguna to Octavia)
- Expect continuous work from Monday, January 13 to Tuesday, January 19
- Work hours: 10AM to 6PM
- Lining hours: 7AM to 4PM
Oak Street (Octavia to Gough)
- Expect continuous work from Monday, January 20 to Tuesday, January 21
- Work hours: 10AM to 6PM
- Lining hours: 7AM to 4PM
Oak Street (Near Gough)
- Expect continuous work from Wednesday, January 22 to Friday, January 24
- Work hours: 10AM to 6PM
Access to properties will be maintained. Expect noise, vibration, and odor impacts while this work is being completed.
Please check this project page for timely updates about the construction schedule and upcoming locations. To receive these updates via email, please complete the form on the right hand side of this page.