Active Alerts

If you are experiencing a water, power, or sewer emergency or service problem call our 24-hour hotline at 3-1-1 or (415) 701-2311 from outside SF or log on at sf311.org. Learn more or review active service alerts.

Sewer Upgrades: Renewal & Replacement Program

For Today, Tomorrow and Decades to Come

We strive to minimize disruption and to provide our neighbors with timely and accurate status updates. Public notices have been mailed to the work areas listed.
If you are experiencing a water, power, or sewer emergency service issue call our 24-hour hotline at 3-1-1 or log on at sf311.org.

Streets listed show day work, see the planned night work webpage if you've received a Night Notice.

A reliable system requires maintenance. SFPUC-led infrastructure projects partner with many agencies to dig once and work efficiently. However, coordination challenges and/or unforeseen complications (e.g. unstable soil conditions) may result in delays. A pause in work occurs between sewer upgrade inspections and street restoration.

Thank you for your patience as we upgrade our critical infrastructure to be resilient and reliable. For more information, contact us at: ssip@sfwater.org or 888-581-PIPE (7473).

Can't find any information about the work on your street? see Contacts and Resources below.


Construction is listed by Street | Project Number | Supervisorial District Number

 

Anza Street (22nd Ave. to 23rd Ave.) | WW-729 | D1
Sewer upgrades complete, PGE coordination in-progress, round-about re-design and road restoration TBD.

Baltimore Street (Cordova St. to Naylor St.) | WW-720 | D11
Sewer upgrades in progress, rocky conditions in trench work restoration. Paving and estimated completion June.

Beach Street (Hyde St. to Columbus Ave.) | WW-709 | D2, D3
Paused due to PG&E underground work, water utility conflict and re-design items. Sewer upgrades anticipated to resume TBD. Estimated sewer work duration 5 months.

Beulah Street (Stanyan St. to Schrader St.) | WW-730 | D1
Water lines adjusted. Sewer catch-basins and road restoration resume. Est completion early June.

Bryant Street (3rd St to Ritch St. to Zoe St.) | WW-730 | D6
Paused due to lining schedule, night lining anticipated TBD, estimated duration 2 months.

Buchanan Street (Marina Blvd to No. Point St.) | WW-727 | D2
Sewer upgrades anticipated to begin May, estimated completion July.

Clayton Street (Fulton St. to Grove St.) | WW-727 | D5
Sewer upgrades complete, inspections in progress, estimated completion mid-May.

College Avenue (Saint Mary's Aves to Mission St. | WW-729 | D8
Sewer upgrades anticipated to begin mid-May, estimated duration 1 month.

Cook Street (Geary Blvd. to end) WW-729 | D2
Sewer upgrades complete, inspections in-progress, final road restoration TBD.

Columbus Avenue (Beach to Leavenworth streets) | WW-709 | D2, D3
Sewer upgrades complete, inspections in-progress, final road restoration TBD.

Columbus Avenue (Beach to North point streets) | WW-709 | D2, D3
Paused, pending re-design, estimated duration 5 months, estimated completion TBD.

Excelsior Avenue (Madrid St. to Lisbon St.) | WW-730 | D11
Sewer upgrades complete, inspections in-progress, final road restoration TBD.

Fillmore Street (Union St to Pixley St.) | WW-727 | D2
Sewer upgrades anticipated to begin early June, estimated completion August.

Francisco Street (Richardson St. to Baker St. | WW-729 | D2
Sewer upgrades complete, inspections in-progress, final road restoration TBD.

Francisco Street (Broderick St. to Divisadero St. | WW-729 | D2
Sewer upgrades anticipated to begin April, pending MUNI coordination, estimated duration 1 month.

Federal Street (at Delancy St.| South End Historical District) | WW-730 | D6
Sewer upgrades anticipated to begin May, estimated duration 1 month.

Gates Street (Ogden Ave. to Tompkins Ave.) | WW-720 | D9
Paused due to water service upgrades TBD, street partially restored till sewer upgrades continue TBD.

Greenwich Street (Franklin St. to Polk St. | WW-729 | D3
Sewer upgrades in-progress, estimated completion mid-May.

Greenwich Street (Van Ness Ave. to Polk St. | WW-729 | D3
Sewer upgrades in-progress, water line issue to resolve, estimated completion early June.

Holladay Ave (Costa St. to Rutledge St.) | WW-720 | D9
Sewer upgrades anticipated June.

Jones Street & Jefferson St. Intersection | WW-709 | D3
Delayed due to poor soil conditions. Anticipated to resume May.

Jones Street (Beach St. to Northpoint St.) | WW-709 | D3
Delayed due to poor soil conditions. Anticipated to resume May, estimated duration 3 months.

Jones Street (Clay St. to Sacramento St.) | WW-729 | D3
Delayed due to poor soil conditions and PGE coordination. Anticipated to resume May, estimated duration 3 months.

Kansas Street (22nd St. to Hillside St.) | WW-720 | D6
Sewer upgrades anticipated June.

Larkin Street (Beach St. to Northpoint St.) | WW-709 | D2
Delayed due to poor soil conditions. Anticipated to begin TBD, estimated duration 2 months.

Mangels Street (Detroit St. to Congo St.) | WW-720 | D7
Sewer upgrades in-progress, estimated duration 2 months.

Marina Boulevard & Yacht Road | WW-709 | D2
Delayed due to poor soil conditions. Sewer upgrades 68% Complete. Anticipated to resume TBD, estimated duration 2 months.

Marina Boulevard (Baker St. to Lyon St.) | WW-709 | D2
Delayed due to poor soil conditions. Anticipated to resume TBD, estimated duration 2 months.

Northpoint St. (Jones St. to Columbus Ave.) | WW-709 | D3
Sewer upgrades in-progress, estimated duration 3 months. Delays due to poor soil conditions.

Northpoint St. (Hyde St. to Leavenworth St.) | WW-709 | D2
Sewer upgrades in-progress, estimated duration 3 months. Delays due to poor soil conditions. 

Pacific Avenue (Scott St. to Divisadero St.) | WW-727 | D2
Sewer upgrades in progress, estimated duration 2 months.

Pennsylvania Street (18th St. to Mariposa St.) | WW-729 | D10
Sewer upgrades anticipated to begin late-May, estimated duration 1 month.

Pierce Street (Filbert St. to Union St.) | WW-727 | D2
Sewer upgrades in-progress, estimated duration 2 months.

Pixley Street (Webster St. to Buchanan St.) | WW-720 | D2
Sewer upgrades complete, design pause - lateral work pending, road restoration TBD.

Prague Street (Russia Ave. to Persia Ave.) | WW-720 | D11
Sewer upgrades anticipated to begin mid-May, estimated duration 2 months.

Prentiss Street (Ogden to Tomkins avenues) | WW-730 | D9
Sewer upgrades in-progress, anticipated completion end-June.

San Carlos Street (19th St. to 20th St.) | WW-730 | D9
Sewer upgrades and night lining complete, inspections in progress, road restoration TBD.

San Jose Street and 26th St Intersection | WW-730 | D8
Sewer upgrades anticipated summer 2026

Scott Street (Pacific St. to Broadway St.) | WW-729 | D2
Paused due to AT&T and PG&E coordination, estimated duration 2 months.

Steiner Street (McAllister St. to Fulton St.) | WW-730 | D5
Sewer upgrades and night lining complete, inspections in progress, road restoration TBD.

Yacht Road (Marina Blvd. to end) | WW-709 | D2
Delayed due to poor soil conditions. Anticipated to resume TBD, estimated duration 2 months.